tea party 2025 progress report

2024 BATHROOM RENOVATIONS

2025 TOILET AND FLOORING RENOVATION

2026 CCTV AND SECURITY ENHANCEMENT PROJECT

WHAT'S NEW AT THE FCJ CENTRE

2024 BATHROOM RENOVATIONS

We're thrilled to share some exciting news, especially with our generous donors: our bathroom renovation at FCJ Christian Life Centre has been successfully completed!

Aside from our general donors and tea party donors, we would like to especially thank the FCJ Society and the Community Facility Enhancement Program (CFEP) of the Government of Alberta for helping us fund this project and making it happen.

 

Features:

 

Third-floor bathrooms:

  • 7 regular bathtubs

  • 2 new accessible bathrooms

  • 4 shower rooms

 

Second-floor bathrooms:

  • 12 shower rooms

  • 1 regular bathtub

 

This project marks a significant milestone in our ongoing efforts to provide comfort and convenience for all our guests.

 

Thank you for your ongoing support and generosity.

Warm regards,

FCJ Centre Team

BATHROOMS

BEFORE

Old Shower 2.jpg
Old Bathrooms 1.jpg

AFTER

New Accessible Bathrooms 2.jpg
New Bathrooms 2.jpg

SHOWER ROOM

BEFORE

Old Shower 3.jpg
Old Shower 1.jpg

AFTER

New Shower 12.jpg
New Shower 1.jpg

NEW ACCESSIBLE BATHROOMS

New Accessible Bathrooms 1.jpg
New Accessible Bathrooms 2.jpg

2nd FLOOR PHOTOS

BEFORE

AFTER

Room 249 Pic 2.jpeg
Room 251 Pic 2.jpeg
PXL_20240502_210048619.jpg
PXL_20240502_210124322.jpg

More Bathroom and Ladies Flooring Update

Last summer through October this year, we continued moving forward with our improvement project, focusing in making our space more accessible, welcoming and sustainable for everyone who walks through our doors. We are grateful to share the progress that has been made so far.

We installed three new toilets on the main floor and upgraded the old linoleum to a luxury vinyl tile (LVT) flooring which is water-resistant and non-slip. To ensure greater accessibility, we also added a push-button entry to one of the washrooms, making it fully barrier-free.

In the basement, we replaced the flooring in the large dining room, west dining room, and hallway with high-quality LVT which is also water-resistant and non-slip. We upgraded three toilets in the basement female washrooms, converting one into a completely barrier-free space and installing an additional push-button entry for ease and dignity.

What’s next?

We are now preparing for the final phase of this project: upgrading the basement male washrooms. With each step, we move closer to ensuring that our Centre remains a place of hospitality, accessibility, and care for all. Without your support, these improvements would not be possible, and the Centre is truly grateful for your unwavering dedication towards our Mission.

Guest Bathroom Renovation Complete, More Upgrades on the Way

Happy Easter from all of us at the FCJ Centre!

We’re happy to share some good news with you, our friends, donors, and supporters. The first phase of our guest bathroom renovation is now complete!

Thanks to your generosity, and with the support of the Community Facility Enhancement Program (CFEP) from the Government of Alberta, we’ve been able to make some much-needed improvements.

Here’s what’s been done so far:

  • 26 new toilets have been installed in the guest bedrooms on the 2nd and 3rd floors (13 on each floor).

  • We’ve also replaced the old linoleum with luxury vinyl tile (LVT) flooring, a safer, more durable, and more comfortable option for our guests.

 

The original toilets were over 45 years old and used up to 12 litres of water per flush. Our new water-saving models use just 4.8 litres, helping us reduce our water use and be more environmentally conscious.

What’s next?

This summer, we’ll continue the upgrades by renovating the main floor and basement common washrooms, another step toward making our space more accessible, welcoming, and sustainable for everyone.

While these changes may seem simple, they speak to something deeper: our ongoing commitment to hospitality, care, and stewardship.

Thank you again for walking alongside us.

BEFORE

DSC01393.JPG
DSC01385.JPG
DSC01388.JPG
DSC01396.JPG
DSC01391.JPG

AFTER

DSC01401.JPG
DSC01405.JPG
DSC01399.JPG
DSC01404.JPG
DSC01408.JPG

Security Enhancement Project – Progress Update

We are grateful to share that significant progress has been made on our Security Enhancement Project, supported by funds raised through the Tea Party fundraiser and our capital campaign.

 

All electrical work has been completed this month, preparing the FCJ Centre for the installation of new CCTV cameras and security gates. A third-party security company will carry out the installation in the first two weeks of January, with staff training taking place at the same time.

 

These improvements reflect our commitment to being a place of welcome, care, and safety for all who come through our doors. Thank you for your generosity and continued support in helping us steward this space with responsibility and compassion. We will keep you posted once the project is complete.